Case Study 1
Problem
A construction company working on the Channel Tunnel Rail Link had accumulated, over a period of time, numerous
unidentified chemicals. Our remit was to identify, segregate, manage and dispose of waste in accordance with all relevant
legislation. This included sampling, analysis, risk assessments and disposal route auditing.
Operation
We identified numerous drums that were unsafe for transportation and incorrectly segregated. Our in house chemist proposed a suitable method of safe working and storage, before controlling the removal off site.
Conclusion
The site was left clean from any contamination and full legal documentation was provided to the client, including our
proposals for an ongoing waste programme to keep the waste at a manageable level. This solution was adopted until the
end of the construction project.